Mosier Creek Structure (Rehabilitation)
- Early June – Site mobilization (minimal delays)
- Late June/ Early July – Construct scaffolding system (20 minute delays)
- July/August/Sept/Oct – Concrete rehabilitation work below bridge deck (one way yield signs @ bridge)
- Early Nov – Remove Scaffolding (20 minute delays)
- Late Nov – Deck resurfacing work (4 days of 1 hr delays)